Time Lines

Phase 1 – Requirement Finalization, Hardware & Firmware Design (6 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 1Requirement FinalizationFinalize technical requirements and performance targets.Final Requirement DocumentHardware + Firmware Team
Week 2Component SelectionSelect sensor, LoRa (Mesh) SoC, PMIC, and components.Approved BoMHardware Team
Week 3Firmware ArchitectureDefine firmware stack and power management logic.Firmware Design DocumentFirmware Team
Week 4Schematic DesignDevelop complete circuit schematic.Schematic DocumentHardware Team
Week 5PCB Layout Design4‑layer PCB design with EMI optimization.PCB Layout FilesHardware Team
Week 6Latch/Switch IntegrationIntegrate magnetic/IMU wake‑sleep circuit.Schematic + PCB FilesHardware Team

Phase 2 – Prototype Development and Lab Testing (8 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 7Component ProcurementOrder and receive selected components.Stocked ComponentsProcurement Team
Week 8–9PCB Fabrication – Batch 1Manufacture 5 prototype units.5 Assembled UnitsProduction Team
Week 10PCB Assembly – Batch 1Assemble PCBs.Assembled PCBsHardware Team
Week 11–12Bring‑Up & Initial TestingPower‑on, sensor, communication bring‑up.Initial Bring‑Up ReportHardware Team
Week 13–14Firmware Development Cycle 1Develop base firmware (LoRa Mesh, power, OTA).Test Firmware BuildFirmware Team
Week 15Functional Testing – Batch 1Accuracy, signal, power, wake‑sleep tests.Functional Test ReportHardware + Firmware Team

Phase 3 – Internal and Field Testing (8 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 16–17PCB Fabrication – Batch 2Manufacture 20 units for pilot testing.20 Assembled UnitsHardware Supplier
Week 18Internal Lab TestingEnvironmental, robustness, signal strength validation.Internal Test ReportFirmware + Hardware Team
Week 19–20Firmware Development Cycle 2Refine stability, OTA, encryption.Updated Firmware BuildFirmware Team
Week 21Field Setup – Batch 2Deploy pilot units.Deployment ReportDeployment Team
Week 22Performance TestingDetect accuracy, false positives/negatives, RF quality.Field Test ReportFirmware Team
Week 23Battery Performance ValidationLong‑duration battery tests.Battery Test ReportHardware + Firmware Team
Week 24Field Testing – Batch 3Final extended evaluation.Final Test ReportDeployment Team

Phase 4 – Pre‑Certification & Handover (2 Weeks)

WeekTaskDescriptionDeliverable (Internal)Responsibility
Week 25Performance Issue ResolutionFix issues and finalize improvements.Resolution LogHardware + Firmware Team
Week 26Certification Readiness & HandoverPrepare CE/FCC documents, final handover.Certification PackageTechnical Architecture Team